US 61 Superstreet

Project # MA-22-06 | updated April 8, 2022

Design

Project name: US 61 SuperStreet - Phase I
Design firm: TBD
Pct complete design: 0%
Row parcels needed: 5
Row parcels acquired: 0

Construction

Contractor name:
Contract duration:
Construction status: Up Next for Design

Costs

Design cost:
Row cost: $0.00
Enviro mitigation cost: $0
Construction cost estimate:
Construction bid:
Inspections cost:
Material testing cost:

Funding

Funding federal: $1,580,000
Funding state:
Funding local: ($1,580,000.00)
Funding traffic impact fees:

US 61 / Airline Highway through Ascension Parish is undergoing design to upgrade it to a “super street.”

This entails numerous turn lane and intersection improvements. These are grouped into five segments as depicted on the graphic below.

Use + and - to zoom in and out. Pan with mouse or touch.


icon