Churchpoint Rd. at Roddy Rd. Roundabout

Project # ENG-12-025 | updated October 30, 2019

This improvement will construct a new roundabout at the intersection Churchpoint and Roddy Roads. The project has been restarted with Final Design being almost complete. Right-of-way acquisition is underway and when complete the Utility Relocation will begin.

Below is a conceptual drawing of the proposed roundabout.

photo

Schedule

Current Phase: Final Design and Right-of-Way acquisition
Design Start Date: 2/7/2018
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 0 of 4
f. Final Design yes 98%
g. Utility Relocations yes 0 of 7
h. Construction yes 0%

Team

Contractor: To be Determined following public bid
Design Consultant: Fenstermaker

Budget

Redesign Contract Amount: $90,700
Construction Cost Estimate: To be Determined pending Final Design

Funding for this roundabout is federal, which adds a layer of complexity and lengthens pre-construction activities. This roundabout joins two segments of Roddy Road receiving a Safety Widening utilizing local funding which allows that aspect of the road project to proceed more quickly.

Gallery