Duplessis Rd. Safety Widening

Project # MA-17-10 | updated September 6, 2019

This project will widen Duplessis Rd. from US 61 (Airline Highway) to LA 73.

The project location is depicted by the image below.

photo

Schedule

Current Phase: Preliminary Design
Design Start Date: April 2018
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 30%
e. Right-of-Way Acquisition yes 0 of 82
f. Final Design yes 0%
g. Utility Relocations yes 0 of 8
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Meyer Engineers

Budget

Redesign Contract Amount: $591,830
Construction Cost Estimate: To be Determined