C Braud Rd. Safety Widening (LA 73 to Bluff Rd)

Project # MA-17-11 | updated September 6, 2019

This project will widen C Braud Rd. for safety improvement from Bluff Road to LA Hwy 73. The project is approximately 1 mile in length.

The image below displays the location of the project.

photo

Schedule

Current Phase: Final Design
Design Start Date: December 2017
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 12 of 20
f. Final Design yes 98%
g. Utility Relocations yes 0 of 6
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Hartman Engineering, Inc.

Budget

Redesign Contract Amount: $511,115
Construction Cost Estimate: To be Determined