Parker Rd. at PR 929 (Hornsby Rd.) Roundabout

Project # MA-17-03 | updated September 6, 2019

A roundabout will be installed at the intersection of Parish Road 929 (Hornsby Rd.) and Parker Road, replacing the 4-way stop. This will improve traffic flow through the intersection.

The image below displays the project location.

photo

Schedule

Current Phase: Pre-Construction
Design Start Date: October 2017
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 0 of 10
f. Final Design yes 75%
g. Utility Relocations yes 0 of 7
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Buchart Horn

Budget

Redesign Contract Amount: $456,495
Construction Cost Estimate: To be Determined

This project is tied to $1M in DOTD Safety funds and DOTD’s pre-construction process.