Tiggy Duplessis Safety Widening

Project # MA-17-09 | updated September 6, 2019

The 1-12 mile length of Tiggy Duplessis Road from LA 621 to Duplessis Rd. will be widened for safety improvements.

The project location is displayed below.

photo

Schedule

Current Phase: Final Design
Design Start Date:
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 0 of 48
f. Final Design yes 30%
g. Utility Relocations yes 0 of 7
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Meyer Engineers

Budget

Redesign Contract Amount: $451,725
Construction Cost Estimate: To be Determined