Hwy 929 at Braud Road Roundabout

Project # MA-18-02 | updated September 6, 2019

This project will construct a roundabout at the intersection of Parish Road 929 and Braud Road, replacing the 4-way stop. This will improve traffic flow through the intersection.

The location of this project is depicted below.

photo

Schedule

Current Phase: Final Design
Design Start Date: April 2018
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 0 of 6
f. Final Design yes 80%
g. Utility Relocations yes 0 of 6
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: BKI

Budget

Redesign Contract Amount: $485,050
Construction Cost Estimate: To be Determined