Project # MA-18-01 | updated September 6, 2019
This project will widen 2 miles of Germany Road from Hwy. 44 to US 61 providing safety improvements.
The image below shows the location of this project.
Schedule
Current Phase: Preliminary Design
Design Start Date: March 2018
Construction Start Date: To be Determined
Status
Task | Required? ![]() |
Complete | |
---|---|---|---|
a. Land / Topo Survey | yes | 100% | |
b. Subsurface Utility Eng. | yes | 100% | |
c. Geotechnical Testing | yes | 100% | |
d. Preliminary Design | yes | 60% | |
e. Right-of-Way Acquisition | yes | 0 of 72 | |
f. Final Design | yes | 0% | |
g. Utility Relocations | yes | 0 of 7 | |
h. Construction | yes | 0% |
Team
Contractor: To be Determined
Design Consultant: Evans-Graves
Budget
Redesign Contract Amount: $624,709
Construction Cost Estimate: To be Determined