Germany Rd. at US 61 Turn Lanes

Project # MA-18-05 | updated September 6, 2019

This project will improve the intersection of Germany Road at US 61 to include left, thru and right turn lanes.

This project is linked to DOTD traffic signal review and approvals. The location is illustrated below.

photo

Schedule

Current Phase: Final Design
Design Start Date: March 2018
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 6 of 8
f. Final Design yes 90%
g. Utility Relocations yes 0 of 7
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Evans-Graves

Budget

Redesign Contract Amount: $174,260
Construction Cost Estimate: To be Determined

Gallery