Airline Hwy. Signal Sync

Project # MA-17-08 | updated September 6, 2019

This task order is a planning effort to facilitate better traffic flow along Airline Highway - one of Ascension Parish’s major corridors. The signalization of 19 intersections was studied.

Now complete, this optimized signal synchronization has been implemented by the LA DOTD for better traffic flow along Airline Highway (US 61).

photo

Schedule

Current Phase: 100% complete
Design Start Date: October 2017

Status

Task Required? space Complete
a. Land / Topo Survey no n/a
b. Subsurface Utility Eng. no n/a
c. Geotechnical Testing no n/a
d. Preliminary Design no n/a
e. Right-of-Way Acquisition no none
f. Final Design no n/a
g. Utility Relocations no none
h. Construction no n/a

Team

Design Consultant: Neel Schaffer

Budget

Study Contract Amount: $64,652

Gallery