Project # MA-18-07 | updated June 28, 2021
Design
Project name: Braud Rd @ Germany Rd RoundaboutDesign firm: T. Baker Smith
Pct complete design: 98%
Row parcels needed: 24
Row parcels acquired: 24
Construction
Contractor name:Contract duration:
Construction status: Design and Clearing & Grubbing are Complete
Costs
Design cost: $414,940.00Row cost: $535,154.90
Enviro mitigation cost: $0
Construction cost estimate: $1,604,778.56
Construction bid:
Inspections cost:
Material testing cost:
Funding
Funding federal:Funding state:
Funding local: $2,554,873.46
Funding traffic impact fees: