C Braud Rd. Safety Widening (LA 73 to Bluff Rd)

Project # MA-17-11 | updated June 15, 2021

Design

Project name: C Braud Widening (LA 73 - LA 928)
Design firm: Hartman
Pct complete design: 100%
Row parcels needed: 20
Row parcels acquired: 20

Construction

Contractor name: Command Construction
Contract duration: 200
Construction status: Under Construction

Costs

Design cost: $608,180.00
Row cost: $391,656.00
Enviro mitigation cost: $0
Construction cost estimate: $3,143,013.82
Construction bid: $2,051,182.89
Inspections cost: $157,885.80
Material testing cost: $18,118.24

Funding

Funding federal:
Funding state:
Funding local: $4,318,853.86
Funding traffic impact fees:

This project will widen C Braud Rd. for safety improvement from Bluff Road to LA Hwy 73. The project is approximately 1 mile in length.

The image below displays the location of the project.