Project # MA-21-01 | updated February 7, 2021
A new connector road is being planned to link LA 30 to “Buzzard Roost”, also known as N. Robert Wilson Rd.
An air photo showing the approximate position of this future road project is depicted below.
Schedule
Current Phase: Preconstruction
Design Start Date: 2020
Construction Start Date: To be Determined
Status
Task | Required? ![]() | Complete | |
---|---|---|---|
a. Land / Topo Survey | yes | 50% | |
b. Subsurface Utility Eng. | yes | 45% | |
c. Geotechnical Testing | yes | 0% | |
d. Preliminary Design | yes | 0% | |
e. Property Survey | yes | 0% | |
f. Right-of-Way Maps | yes | 0% | |
g. Final Design | yes | 0% | |
h. Utility Relocations | unkn. | 0% | |
i. Bidding | yes | 0% | |
j. Construction | yes | 0% |
Team
Contractor: To be Determined
Design Consultant: _________________
Budget
Predesign Contract Amount: Pending
Construction Cost Estimate: To be Determined