LA 73 Turn Lane at Brown Rd

Project # MA-18-03a | updated January 24, 2021

Turn lanes will be added to Hwy. 73 southbound at Brown Road.

The design project was split into a “A” and “B” portions as it moved into the construction phase. This Hwy. 73 at Brown Road turn lane project is identified by the pin labeled “A” in the image below.

photo

Schedule

Current Phase: Construction
Design Start Date: February 2018

Status

TaskRequired? spaceComplete
a. Land / Topo Surveyyes100%
b. Subsurface Utility Eng.yes100%
c. Geotechnical Testingyes100%
d. Preliminary Designyes100%
e. Right-of-Way Acquisitionyes2 of 2
f. Final Designyes100%
g. Utility Relocationsyes5 of 5
h. Constructionyes90%

Team

Contractor: Command Construction Industries, LLC
Design Consultant: Neel Schaffer

Budget

Redesign Contract Amount: $331,071
Construction Cost: $734,918.26