LA 73 Turn Lanes at Brown and Oakland

Project # MA-18-03 | updated September 6, 2019

Turn lanes will be added to Hwy. 73 southbound at Oakland Drive and Brown Road. Turn lanes will also be added from Brown and Oakland onto LA 73.

The locations of intersections improved by this project are depicted below.

photo

Schedule

Current Phase: Final Design
Design Start Date: February 2018
Construction Start Date: To be Determined

Status

Task Required? space Complete
a. Land / Topo Survey yes 100%
b. Subsurface Utility Eng. yes 100%
c. Geotechnical Testing yes 100%
d. Preliminary Design yes 100%
e. Right-of-Way Acquisition yes 5 of 5
f. Final Design yes 98%
g. Utility Relocations yes 3 pf 5
h. Construction yes 0%

Team

Contractor: To be Determined
Design Consultant: Neel Schaffer

Budget

Redesign Contract Amount: $331,071
Construction Cost Estimate: To be Determined