Project # MA-18-03 | updated September 6, 2019
Turn lanes will be added to Hwy. 73 southbound at Oakland Drive and Brown Road. Turn lanes will also be added from Brown and Oakland onto LA 73.
The locations of intersections improved by this project are depicted below.
Schedule
Current Phase: Final Design
Design Start Date: February 2018
Construction Start Date: To be Determined
Status
Task | Required? ![]() |
Complete | |
---|---|---|---|
a. Land / Topo Survey | yes | 100% | |
b. Subsurface Utility Eng. | yes | 100% | |
c. Geotechnical Testing | yes | 100% | |
d. Preliminary Design | yes | 100% | |
e. Right-of-Way Acquisition | yes | 5 of 5 | |
f. Final Design | yes | 98% | |
g. Utility Relocations | yes | 3 pf 5 | |
h. Construction | yes | 0% |
Team
Contractor: To be Determined
Design Consultant: Neel Schaffer
Budget
Redesign Contract Amount: $331,071