MA-18-12 – LA 930 Safety Widening – LA 42 to PR 929 Causey

Project Overview:

LA 930 Widening (LA42-PR 929/Causey Road) Entire Road Re-design

Re-design of DOTD 95% Final Design with Pipeline Relocation Avoidance

View Project on Map

Project Status
Survey 100%
Utility Investigation 100%
Geotechnical 100%
Preliminary Design 100%
ROW Acquisition 100%
Final Design 95%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction : Ongoing
Design Start Date: 12/10/2018
Design End Date: 4/30/2019

 

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: TBD
Design Consultant: T. Baker Smith

Budget and Expenditures

Design Contract Amount:  $164,545

 

Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project Number:  MA-18-12

Task Number: 

Project Length:  2 miles


 