MA-18-08 – LA 930 @ Henry Rd Roundabout

Project Overview:

Converting at 4-way stop-controlled intersection at LA 930 and Henry Road to one with a Roundabout to improve traffic operational flow through the intersection.

View Project on Map

Project Status
Survey 100%
Utility Investigation 100%
Geotechnical 100%
Preliminary Design 40%
ROW Acquisition 0%
Final Design 0%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction : Ongoing
Design Start Date: 5/31/2018
Design End Date: 11/13/2018

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: TBD
Design Consultant: Shread-Kuyrkendall and Associates, Inc. (SKA)

Budget and Expenditures

Design Contract Amount:  $403,815
Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project Number:  MA-18-08

Task Number: 

Project Length:  0.5 Mile


 
Project Photos:

no images were found

 

For questions and comments about the Move Ascension transportation initiative, please send email requests to Michael Enlow   at menlow@apgov.us or use our online feedback form.