MA-18-03 – LA 73 Turn Lanes

Project Overview:

Adding turn lanes on Hwy. 73 Southbound at Oakland Drive and Brown Road as well as turn lanes onto LA 73 from Brown and Oakland.

View Project on Map

Project Status
Survey 65%
Utility Investigation 85%
Geotechnical 40%
Preliminary Design 10%
ROW Acquisition 0%
Final Design 0%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction - Ongoing
Design Start Date: 2 /19/2018
Design End Date: 1/2/2019

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: TBD
Design Consultant: Neel Schaffer

Budget and Expenditures

Design Contract Amount:  $331,071
Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project Number:  MA-18-03

Task Number: Not issued

Project Length:  1.0 Mile


 
Project Photos:

 

For questions and comments about the Move Ascension transportation initiative, please send email requests to Michael Enlow   at menlow@apgov.us or use our online feedback form.