MA-17-04 – Roddy Rd. Safety Widening (LA 931 – LA 933)

Project Overview:

PROJECT DE-SCOPED SEPTEMBER 2018

CURRENT SCOPE:

UPDATE: This project has been halted at the preliminary design phase and descoped. This project will now consist of making select intersection improvements only, based on the most up to date safety plan developed by the CRPC. The bridge at Henderson Bayou is to be replaced with with box culverts and the channel realigned.

PREVIOUS SCOPE:

Part 3 of the Roddy Road Corridor Project, this segment is to be widened for safety from LA 931 to LA 933 with box culverts to replace the bridge at Henderson Bayou and channel realignment. Intersection improvements include:
The addition of Left turn lanes at Roddy/LA 931 on Eastbound, Northbound and Southbound approaches.

View Project on Map

Project Status
Survey 100%
Utility Investigation 100%
Geotechnical 100%
Preliminary Design 100%
ROW Acquisition 0%
Final Design 0%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction
Start Date: 10/6/2017
End Date: 10/6/2018
Duration: 365
Project Look Ahead:

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: 
Design Consultant: SJB Group

Budget and Expenditures

Design Contract Amount: $574,379
Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project No: MA-17-04
Project Length: 2 Miles

 

Project Photos:

 

For questions and comments about the Move Ascension transportation initiative, please send email requests to Michael Enlow   at menlow@apgov.us or use our online feedback form.