MA-18-05 – Germany Road / US 61 Intersection Improvements

Project Overview:

Improving the Germany Road intersection leg at US 61 to include left, thru and right turn lanes.

View Project on Map

Project Status
Survey 100%
Utility Investigation 65%
Geotechnical 100%
Preliminary Design 50%
ROW Acquisition 0%
Final Design 0%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction : Ongoing
Design Start Date: 4 /5/2018
Design End Date: 12/31/2018

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: TBD
Design Consultant: Evans-Graves

Budget and Expenditures

Design Contract Amount:  $174,260
Construction Cost Estimate: TBD
Construction Contract Amount: TBD