Churchpoint/Roddy Roundabout

Project Overview:

Roundabout replacing intersection at Churchpoint and Roddy road. The project is nearly completed with design. This project has been re-started with Final Design being completed along with right-of-way acquisition and Utility Relocation.

View Project on Map

Project Status
Survey 100%
Utility Investigation 100%
Geotechnical 100%
Preliminary Design 60%
ROW Acquisition 0%
Final Design 0%
Construction 0%

 

Project Schedule

Current Phase: Pre-Construction
Start Date: 11/15/2017
End Date: 5/15/2018
Duration: 181
Project Look Ahead:

Construction Timetable

Construction Start Date: TBD
Construction End Date: TBD
Construction Duration: TBD

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: 
Design Consultant: Fenstermaker

Budget and Expenditures

Design Contract Amount: TBD
Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project Number:  N/A
Project Length:  0 Miles


 
Project Photos:

 

For questions and comments about the Move Ascension transportation initiative, please send email requests to Michael Enlow   at menlow@apgov.us or use our online feedback form.