MA-17-05 – Ashland to St. Landry Connector

Project Overview:

New 2 lane roadway connector from St. Landry Ave to Ashland Road just above Lamar Dixon Expo Center.  Project is about 0.5 miles.

View Project on Map

Project Status
Survey 100%
Utility Investigation 100%
Geotechnical 100%
Preliminary Design 100%
ROW Acquisition 100%
Final Design 65%
Construction 0%

 

Project Schedule
Concept Pre-Design Design Permits ROW Construction Complete
  9/25/2017         9/25/2018

 

Construction Timetable
Contractor Notice to Proceed Projected Completion
To be determined Future Future

*Construction Schedules will not be available until after the project is designed, bid and awarded.

Project Team

Contractor: 
Design Consultant: Volkert

Budget and Expenditures

Design Contract Amount: $274,875.00
Construction Cost Estimate: TBD
Construction Contract Amount: TBD

Specifications

Project Number: MA-17-05
Project Length: 0.50 Miles


 
Project Photos:

 

For questions and comments about the Move Ascension transportation initiative, please send email requests to Michael Enlow  at menlow@apgov.us or use our online feedback form.