Projects

Phase 1 – Immediate Action Projects (Funded Through Construction)

  1. Roddy Road Safety Widening (US 61-LA 935 including intersection improvements at LA 429 and LA 935)
  2. Roddy Road Safety Widening (LA 935-LA 621 including intersection improvements at LA 621 and LA 934)
  3. Roddy Road Safety Widening (LA 931- LA 933 including intersection improvement at LA 931)
  4. Parker Road @ Parish Road 929 Roundabout
  5. Ashland Road – St. Landry Connector (New Roadway)
  6. Henry Road Safety Widening (LA 73 – Tillotson Rd/Aikens Rd)
  7. Churchpoint/Roddy Roundabout

Phase 2 – (Pre-Construction Design funding)

  1. C Braud Rd. (Bluff to Hwy 73)

 

Move Ascension
Milestone Status / % Complete
CDC Project  Survey Underground Utility Investigation Geotechnical Borings Preliminary Design Final Design R/W Acquisition
               
T. Baker Smith Roddy Road (LA935-LA621) 100% 100% 100% 60% 0% 0%
Shread (SKA) Roddy Road (US 61-LA935) 100% 100% 100% 40% 0% 0%
SJB Roddy Road (LA 933 – LA 931) 50% 25% 0% 0% 0% 0%
GSA Henry Road Widening (LA 73-Tillotson) 100% 100% 100% 25% 0% 0%
Buchart Horn PR 929/Parker Roundabout 100% 100% 100% 25% 0% 0%
Volkert Ashland Rd -St.Landry Ave Connector 100% 100% 100% 60% 0% 0%
Neel-Shaffer Six (6) Intersection Traffic Analyses N/A N/A N/A 100% 0% 0%
Neel-Shaffer US 61 Signal Timing N/A N/A N/A 100% 0% 0%
Hartman Engr. C Braud (LA 73 – Bluff Rd) 75% 25% 0% 0% 0% 0%