Phase 2 Projects

Phase 2 – (Pre-Construction Design funding)

  1. C Braud Rd. (Bluff to Hwy 73)

 

Move Ascension – Phase 2
Milestone Status / % Complete
CDC Project  Survey Underground Utility Investigation Geotechnical Borings Preliminary Design Final Design R/W Acquisition
               
               
Hartman Engr. C Braud (LA 73 – Bluff Rd) 75% 25% 0% 0% 0% 0%